Petition to Increase Simple-Cycle Operating Hours for the Sunrise Power Project
    8 Documents in Project
    
        
            
        
            
        
            
        
            
        
            
                
            
        
            
                
                
            
    
    
            
                
                    
                
                    
                
                    
                    
                                    
                        
                                    
                        
            
        
    
        
            
                
    
        
        
            
                
                    
                    
                        
                                    
                        
                            
                        
                    
                            
        
        
            
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
            
        
    
                Summary
                SCH Number
            
            
                2000129017
            
        
                    Lead Agency
            
            
                California Energy Commission
                
            
        
                Document Title
            
            Petition to Increase Simple-Cycle Operating Hours for the Sunrise Power Project
        
                Document Type
            
            
                NOD - Notice of Determination
            
        
                Received
            
            
                    Posted
                
                
                    1/8/2002
                
            
                Document Description
            
            Post-certification project change: Clarification of potential conflicts between air quality conditions of certification AQ-10, -14 & -15 regarding the definition of startup period and Continuous Emission Monitoring (CEM).
        Contact Information
                        Name
                    
                    
                        Nancy Tronaas
                    
                
                        Agency Name
                    
                    
                        California Energy Commission
                    
                
                        Contact Types
                    
                    
                        Lead/Public Agency
                    
                
                            Phone
                        
                        
                    
                            Email
                        
                        
                    Location
                    Counties
                
                Kern
            Notice of Determination
                        Approving Agency
                    
                    
                        California Energy Commission                                    
                    
                
                            Approving Agency Role
                        
                        
                            Lead Agency
                        
                    
                            Approved On
                        
                        Determinations
                            (1) The project will have a significant impact on the environment
                        
                        
                            No
                        
                    
                            (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            No
                        
                    
                            (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            No
                        
                    
                            (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            No
                        
                    
                            (3) Mitigated measures were made a condition of the approval of the project
                        
                        
                            Yes
                        
                    
                            (4) A mitigation reporting or monitoring plan was adopted for this project
                        
                        
                            N/A
                        
                    
                            (5) A Statement of Overriding Considerations was adopted for this project
                        
                        
                            No
                        
                    
                            (6) Findings were made pursuant to the provisions of CEQA
                        
                        
                            N/A
                        
                    Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.
