SCH Number 2018042078


Project Info

Title
Central Reservoir Replacement Project
Description
The Project includes demolition of the existing 154-million gallon (MG) open-cut reservoir and material storage building; earthwork and subsurface preparation; construction of a reinforced tank foundation, three 17 MG concrete tanks within the existing reservoir basin, valve structure, drainage basin; and abandonment of existing monitoring wells. The Project also includes moving an existing rate control station currently located below ground at the corner of 25th Avenue and East 29th Street onto the Project site. The current access road around the reservoir perimeter would be retained and improved. The Project will also remove vegetation, replace security fencing, and restore and landscape the site following construction. The Project also includes an access driveway to connect the Redwood Day School parking area to Ardley Avenue.
Download CSV New Search

 

2 documents in project

Type Lead/Public Agency Received Title
East Bay Municipal Utility District Central Reservoir Replacement Project
East Bay Municipal Utility District Central Reservoir Replacement Project